Province | Subbasin | % |
---|---|---|
Mountain Snake | Salmon | 100.00% |
Previous: | Next: |
---|---|
74017 REL 13: 1996-043-00 EXP JCAPE O&M |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Environmental Compliance Documentation | B: 165. Produce Environmental Compliance Documentation | 12/31/2019 | 12/31/2019 | |
BY 2017 Smolt Release | C: 176. BY 2017 production activities for the Johnson Creek Supplementation Program | 04/15/2019 | 03/29/2019 | |
BY 2018 Johnson Creek Supplementation Juvenile Rearing | D: 176. BY 2018 production activities for the Johnson Creek Supplementation Program | 12/31/2019 | 12/31/2019 | |
BY 2019 Supplementation Activities | E: 176. BY 2019 production activities for the Johnson Creek Supplementation Program | 12/31/2019 | 12/31/2019 | |
Nutrient Enhancement in Johnson Creek | F: 44. Nutrient Enhancement in Johnson Creek | 09/30/2019 | 09/11/2019 | |
Maintain Hatchery Facilities | G: 61. Hatchery Facilities Maintenance | 12/31/2019 | 12/31/2019 | |
Project Information Presentations | H: 161. Project Information Presentations | 12/31/2019 | 12/31/2019 | |
Outreach and Education | I: 99. Conduct outreach and public education efforts | 12/31/2019 | 12/31/2019 | |
Project Coordination | J: 191. JCAPE O&M Project Coordination | 12/31/2019 | 12/31/2019 | |
Update Annual Operating Plan (AOP) | K: 174. Produce Annual Operation Plan and Hatchery Genetic Management Plan | 12/31/2019 | 12/31/2019 | |
Submit BiOp RPA Report in Taurus | L: 202. Johnson Creek spring/summer chinook RPA/BiOp Data Submission to M&E Project Leader | 09/30/2019 | 09/30/2019 | |
Completed Annual Report | M: 132. Prepare Brood Year 2017 Report (May 2017 to April 2019) | 09/30/2019 | 05/31/2019 | |
Completed Annual Report | N: 132. Prepare 2018 Adult Salmon Run Report (June 2018 to December 2018) | 06/30/2019 | 06/30/2019 | |
Effective implementation management and timely contract administration | O: 119. Manage and Administer Johnson Creek O&M Project | 12/31/2019 | 12/31/2019 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 01/01/2019 | ||||||
B | 165 | Produce Environmental Compliance Documentation | 01/01/2019 | ||||||
C | 176 | BY 2017 production activities for the Johnson Creek Supplementation Program | 10/29/2018 | ||||||
D | 176 | BY 2018 production activities for the Johnson Creek Supplementation Program | 10/30/2018 | ||||||
E | 176 | BY 2019 production activities for the Johnson Creek Supplementation Program | 10/30/2018 | ||||||
F | 44 | Nutrient Enhancement in Johnson Creek | 01/01/2019 | ||||||
G | 61 | Hatchery Facilities Maintenance | 10/29/2018 | ||||||
H | 161 | Project Information Presentations | 01/01/2019 | ||||||
I | 99 | Conduct outreach and public education efforts | 01/01/2019 | ||||||
J | 191 | JCAPE O&M Project Coordination | 01/01/2019 | ||||||
K | 174 | Produce Annual Operation Plan and Hatchery Genetic Management Plan | 10/29/2018 | ||||||
L | 202 | Johnson Creek spring/summer chinook RPA/BiOp Data Submission to M&E Project Leader | |||||||
M | 132 | Prepare Brood Year 2017 Report (May 2017 to April 2019) | 01/01/2019 | ||||||
N | 132 | Prepare 2018 Adult Salmon Run Report (June 2018 to December 2018) | 01/01/2019 | ||||||
O | 119 | Manage and Administer Johnson Creek O&M Project | 01/01/2019 |